Nicolas Sehnaoui: November 2012 Update.
Nicolas Sehnaoui wrote Many of you heard of our opening of the new Fiber Optics center in Beirut but asked me to explain more about it.
Tonight I'd like to take a moment and tell you more about this new achievement and where it falls in our national Fiber Optics Plan.
It's the Network Operation Control NOC that we opened simultaneously with the activation of the first Fiber Optic Ring of Greater Beirut Area linking 26 co's.
It is situated in Nahr Area and will allow teams to monitor and control the Fiber Optics network that is being installed all over Lebanon.
The first users to benefit from this 1st Ring in a few months will be the Heavy Users like Educational, Medical and Governmental Institutions.
These Heavy Users will have access to a speed 10 to 20 times faster than current DSL.
Remaining 12 rings will be activated from now till April 2013 and they will connect around 300 Centrales by a strong network of Fiber Optics.
When all Rings are active we will immediatly start equipping villages where there is currently no DSL with the proper equipment.
FTTH (Fiber to the Home) will connect the Citizens directly to this Fiber Optics network and will allow for a totally new level of connectivity.
FTTH tender will be launched on Jan/Feb 2013 to allow a quick Implementation kick off.